What is the connection execution deadline? How can it be improved?

.

The trend of the average connection execution deadlines after payment of estimates has experienced a satisfactory improvement in recent years; from 20 to 5 days, on average. It is thanks to reforms (lower subscription fee, simplification of procedures, etc.)

Unfortunately, due to problems of poles supply, it is becoming increasingly difficult to make connections within the deadline where poles are required. This has an impact on the execution of some connections. As we have said before, we are working with the public authorities to find a solution to this problem of pole supply.