Eneo Cameroon commissions a second power transformer at its Bonabéri substation this Sunday between 5 a.m. and 12:30 p.m.

Eneo Cameroon informs its customers in Bonaberi that it will commission a power transformer at the Bonaberi substation. Connection works and commissioning of the equipment will take place on Sunday, September 4 as from 5 a.m. to 12:30 p.m.

Once the power transformer is installed, it will double the transit capacity of the substation.

The operation will also improve the reliability of the facility. The availability of two transformers at the Bonabéri substation will help in reducing the response time of this facility in case of failure. It will offer the possibility of connecting other customers to the network .

During works  on Sunday at the Bonabéri substation, from 5 a.m. to 12:30 p.m., and for safety reasons, customers in Bonaberi will be disconnected.

Eneo Cameroon recommends that customers should:
         - Disconnect all their devices and
         - To reconnect them only 15 minutes after the effective return of energy.

All our advice on safety and energy saving are available on the Eneo website: www.eneocameroon.cm or through the customer relations center by calling 8010.

For the Regional Director, Douala 

 Télécharger ici la lettre adressée aux autorités et le communiqué radio relatif aux travaux du dimanche 04 septembre 2016 au poste de Bonaberi


image
APPLICATION TRACKING

Evolution and e-Quotation

image
ELECTRONIC INVOICE

Last 12 months Emails & Alerts

image
COMPLAINTS ONLINE

Live tracking and revival

image
INCIDENTS & WORK SCHEDULE

Calendar by city and quarter